These photos were taken during installation and initial testing of the cluster. The system was moved and totally rewired before entering production.
The hallway was narrowed considerably by the row of pallets full of
IBM x335 systems.
Joey Jones installed much of the memory, etc. in the systems as we
unboxed them.
The nodes were stacked in the server room floor while we installed the
rack rails.
This is the Voltaire InfiniBand host channel adapter (HCA).
This is 192 Voltaire host channel adapters waiting to be unboxed and
installed.
The InfiniBand cables were stacked and ready to be installed.
This is the inside of an IBM x335 compute node with the InfiniBand HCA
installed.
<- Main Gallery | Next ->
|
Contact: webmaster@erc.msstate.edu
|